Content |
Page No. |
1.
Index |
1 |
2.
Pre-Approval Sheet |
2 |
3.
Objective |
3 |
4.
Scope |
4 |
5.
Responsibilities |
4 |
6.
Introduction |
5 |
7.
Equipment and Material |
6 |
8.
Air Velocity Test and Calculation of Air Changes Per Hour |
6 |
9.
HEPA Filter Integrity Testing |
9 |
10. Air Flow Pattern Test |
13 |
11. Non-Viable Particulate
Count Test |
14 |
12. Recovery Study |
18 |
13. Differential Pressure
Test |
19 |
14. Temperature Control
Test |
20 |
15. Humidity Control Test |
21 |
16. Light Intensity Measurement:
(Lux Measurement) |
22 |
17. Noise Level
Measurement |
23 |
18. General Requirements |
24 |
19. Annexure |
25 |
20. Reference |
35 |
PREPARED BY |
SIGNATURE |
DATE |
|
|
|
|
|
|
CHECKED BY |
SIGNATURE |
DATE |
|
|
|
|
|
|
APPROVED BY |
SIGNATURE |
DATE |
|
|
|
|
|
|
- Air velocity (ACPH) measurement
- HEPA Filter leak testing (using Hot or Cold DOP)
- Airflow pattern test (Smoke test)
- Nonviable particulate counts measurement
- Recovery test
- Monitoring of Differential pressure of the area
- Monitoring of Temperature within the area
- Monitoring of relative humidity within the area
- Area light level measurement (LUX measurement)
- Area noise level measurement (dB level)
DESIGNATION |
RESPONSIBILITY |
Validation
Head |
Responsible for final review and approval of
protocol and report |
Validation
In charge |
Responsible for perform site work within the
time bond period. |
EDP
Staff |
Responsible for Prepare Report. |
Sr. No. |
Air Handling
Units |
Room
Name |
HEPA
Filters |
Class |
|
|
|
|
|
|
|
|||
|
|
|||
|
|
|||
|
|
|||
|
|
|||
|
|
|
|
|
|
|
|||
|
|
|||
|
|
|||
|
|
|
||
|
|
|
||
|
|
|||
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|||
|
|
- TSI Hot Wire Anemometer / TSI air capture hood
- Photometer with Aerosol generator
- Fog generator (Smoke generator)
- Airborne Non-Viable Particle counter
- Calibrated Temperature & Relative Humidity data logger
- Light level meter-Lux meter
- Noise level meter-dBA meter
CRITERIA |
ACCEPTANCE |
Air
velocity and ACPH |
As
per design NLT + 20 % |
STEP |
ACTION |
1 |
Switch
on the respective air-handling unit (AHU) of the clean room. |
2 |
Ensure
that AHU is operational for the last 5 to 10 minutes. |
3 |
Take
the relevant details, like No. of the filter area, filter size, room volume,
AHU No, design CMH/CFM, and ACPH for each room. |
4 |
Switch
`ON’ the calibrated hot wire Anemometer. Check the “Zero” reading on the
display. |
5 |
Hold
the `velocity measurement’-probe at the working height of 6 inches (approx.150
mm) below the face of the HEPA filter in the clean room. |
6 |
Record
air velocity at different points of the HEPA filter i.e. Four corners and one
center [Terminal HEPA]. For the HEPA filter list with AHU & room |
7 |
Calculate
the average velocity of each filter. |
8 |
Average
air velocity at each point. |
9 |
Record
velocity. [Reference is made to Annexure-I]. |
STEP |
ACTION |
1 |
Measure
the filter face area in square meters. |
2 |
Calculate
the actual volume of supplied air in each room as below. |
3 |
Airflow discharge [m3/minute] = Air velocity of HEPA filter [m/s] X Filter area
[m2] x 60. |
4 |
Calculate
the volume of the room in a cubic meter, of which air changes are to be
calculated. |
5 |
Calculate
the no. of air changes as follows. |
6 |
No.
of ACPH = Airflow discharge in room x 60(CMH) x Room volume. |
7 |
For the filling and sealing area, ACPH should not be less than 300. |
8 |
For
all the Classified areas, ACPH should not be less than 20. |
9 |
If
the air changes in the area are not within the limit, troubleshoot the cause
and rectify it. |
10 |
Engineering
and QA staff should investigate the reason for the deviation. Engineering
will take immediate action to rectify it. |
11 |
Record
the ACPH [Annexure-I]. |
STEP |
ACTION |
1 |
Switch on the respective air-handling unit (AHU)
of the clean room. |
2 |
Ensure that AHU is operational for the last 5
to 10 minutes. |
3 |
Take the relevant details, like No. of the filter area, filter size, room volume, AHU |
4 |
Take the mean velocity reading of each filter
[cfm) by capture hood |
5 |
Calculate the CMH of the room by the sum of all filter cfm
multiply by 60. |
7 |
Calculate the ACPH of the room i.e. |
8 |
Record the ACPH [Annexure-I]. If done by
capture Hood. |
CRITERIA |
ACCEPTANCE |
HEPA Filter Integrity Test With Using Aerosol |
An unacceptable leak is a local reading
greater than 0.01% |
PROCEDURE:
(FOR GENERATION OF AEROSOL):
STEP |
ACTION |
1 |
Check the Aerosol oil level in the Aerosol
generator. |
2 |
Connect Compressed air / Nitrogen gas to the aerosol generator & adjust the pressure regulator to 20PSI. |
3 |
Direct the outlet of the aerosol generator to
return duct [riser] or fresh air intake of AHU. |
4 |
Start the aerosol generator by switching on
the Compressed air / Nitrogen gas to produce the upstream concentration
required for leak detection till the photometer reads the Photometric
concentration of 100%. |
CALIBRATION
OF THE INSTRUMENT [PHOTOMETER]
STEP |
ACTION |
1 |
Put the photometer selector switch on upstream
mode. |
2 |
Connect the tube of the photometer to the upstream
port of the HEPA filter. |
3 |
Wait until the photometer displays 100%
upstream concentration. |
4 |
Remove the tube of the photometer and close the
upstream port of the HEPA filter and ensure fir zero leakage. |
5 |
Put the photometer selector switch on
downstream mode. |
6 |
Wait until the photometer display 0 [ZERO]. |
|
On any installation, the sealing gasket should
be considered as part of the filter and this should be scanned separately
from the filter pack.
|
STEP |
ACTION |
1 |
Ensure that before starting the activity AHU is
operational for 5 to 10 minutes. |
2 |
Ensure that the air velocity, air balancing, and flow adjustments are done before proceeding to the Filter integrity
testing of HEPA filters. |
3 |
Check that a sampling point is provided and
accessible immediately upstream of the filter to be tested. |
4 |
Start the compressed air/nitrogen gas to the Aerosol generator to generate the test aerosol at a minimum of 20 psi and monitor
the pressure. |
5 |
Direct the test aerosol to the riser of the room. |
6 |
Ensure that it is possible to introduce test
aerosol so that 100% concentration can be detected at the upstream sampling
point. |
7 |
Place the aerosol generator in an accessible
position, ideally near the riser, and adjust the aerosol concentration to the
specified density. |
8 |
Prior to the generation of the aerosol place
the photometer probe downstream of the HEPA filter until the instrument has
stabilized. |
9 |
Put the photometer selector switch on upstream
mode. |
10 |
Check the upstream concentration of Aerosol at the port provided for a representative HEPA filter for each room; Until the photometer
displays 100 % upstream. |
11 |
After getting the upstream conc. & put the selector switch to a clear position and close the upstream Aerosol port. |
12 |
Put the photometer selector switch on downstream
mode. |
13 |
Wait until the photometer displays 0. |
14 |
Measure the downstream concentration by
holding the probe at approx.1 inch away from the face of the filter. |
15 |
The photometer has a sample flow rate of 1
cfm. Hold the probe at a distance between 50 to 100 mm from the filter face
and scan the filter and perimeter by passing the probe in slightly
overlapping strokes so that the entire area of the filter and sealing gasket is
sampled. The probe traverse rate should not exceed 10 feet per minute. |
16 |
Observe the percentage of leakage directly on the photometer |
17 |
If any leakage is observed through the sealing of the filter tighten the filter nuts and check again for any leakage. |
18 |
If any leakage is more than 0.01% of the
upstream aerosol concentration then repair it. |
19 |
Repair the patches on filters should not
exceed a maximum of 5% of the total filter face area & maximum width/length of each patch should not be more than 1.5 inches. The total no of patches
should not exceed 5 number/filter. |
20 |
If above-mentioned limit exceeds then replace
the filter & check the integrity of the filter as per the above procedure. |
21 |
Record the result [Annexure-II]. |
CRITERIA |
ACCEPTANCE |
Air flow pattern of
HEPA filter |
Unidirectional |
STEP |
ACTION |
1 |
Start the respective AHU of which the airflow
pattern is to be checked. |
2 |
The person carrying out airflow pattern activity
should follow cleanroom gowning. |
3 |
Fog generators should be used for smoke
generation. |
4 |
During the process, the hands of the operator and the facemask should be covered properly with gloves and a facemask. |
5 |
Expose the smoke at the supply end of the system. |
6 |
Observe the smoke pattern and ensure the
following.
|
7 |
Carry out Videography/ Photography of the
entire airflow pattern-checking activity. |
8 |
Record the result [Annexure-III]. |
CRITERIA |
ACCEPTANCE |
||||
Non-viable
particulate count test |
Grade |
Maximum number of permitted particles per
cubic meter equal to or above |
|||
AT REST |
IN OPERATION |
||||
0.5-5µm |
>5 µm |
0.5-5µm |
>5 µm |
||
A |
3500 |
0 |
3500 |
0 |
|
B |
3500 |
0 |
350000 |
2000 |
|
C |
350000 |
2000 |
3500000 |
20000 |
|
D |
3500000 |
20000 |
Not Defined |
Not Defined |
STEP |
ACTION |
1 |
All components of the
clean air system affecting air quality must be operating in accordance with
the specification and all aspects of the controlled environment, which
contribute to the operational integrity, are complete. |
2 |
Measure on a centered
grid pattern determined by dividing the total floor area, into approximately
equal areas such that:
|
3 |
Calculate the number
of sampling locations with the formula N = Square root of
Room in cubic meters made it to approx. [Reference is made to ISO14644-1]. |
4 |
The sampling location
shall be evenly distributed throughout the area of the cleanroom or clean zone
and positioned at the height of the work activity. In case of additional sampling
locations, their number and position will be specified. |
ESTABLISHMENT
OF SINGLE SAMPLE VOLUME PER LOCATION:
STEP |
ACTION |
1 |
Sample a sufficient volume of air at each location such that a minimum of 20 particles would be detected if the particle concentration for the relevant class were at the class limit for the largest considered particle size. |
2 |
The single sample
volume Vs per location will be determined by Vs =20x1000 / Cnm
Where, Vs = is the minimum
sample volume per location expressed in liters. Cnm =class limit
(number of particles/ m3) for the largest considered particle size specified
for the relevant class. 20 = is the defined
number of particles that could be counted if particle concentration were at
the class limit.
The volume sampled at
each location shall be at least 2 liters with a minimum time at each location
of 1 minute.
Since particle counters operate at a flow rate of 1CFM, which is equal to 28.3 lits per minute, therefore particle analyzed per cubic feet will need to be multiplied with 35.31 to convert to m3. |
3 |
Direct measurement
with 1 M3 particle counter, Specifications are: 50
LPM i.e. 1M3 i.e. 1000 liters per 20 minutes. Sample at each location is taken
for 20 minutes, which is equivalent to 50 LPM i.e. 1M3/20 minutes. Therefore,
for grade A/B/C areas [ISO/5/6/7] and for grade D areas 1 minute per location.
Sampling locations are based on the criticality of the work zone [Reference
is made to Annexure IV]. |
SAMPLING
AT SPECIFIED LOCATIONS AT WORKING HEIGHT:
STEP |
ACTION |
1 |
Start the sampling and take a minimum of single
sample volumes from each location and compute the average particle
concentration at the specified location. |
2 |
Sampling will be conducted at rest and during
operation. |
PARTICLE
COUNTING AT EACH LOCATION:
STEP |
ACTION |
1 |
Switch on the AHU and let it run for 10-15
minutes. |
2 |
Switch `ON’ the particle counter and set the
sampling rate as 1.0 cfm (Approximately 28.0 liters/minute). |
3 |
Hold the particle counter probe to the working
height at different locations of control/critical areas and take the printout of the particle counts of mentioned locations of control/critical areas. |
4 |
Take the particle count at a different location
under HEPA filters covering the total area of the control / critical room as
mentioned in the layout & take printouts of the particle count. |
6 |
Switch OFF the particle counter. |
7 |
Get the report of the particle count by the
external party (Supplier) |
8 |
Such reports should be preserved by the
Quality Assurance department. |
9 |
Particle count test of all control /critical
rooms under AHUs to be carried out once in six months or earlier immediately
after any major change in AHU facility. |
10 |
Record the results and make the trend of
particle count [Reference is made to Annexure IV]. |
CRITERIA |
ACCEPTANCE |
Recovery period |
Not more than 10 minutes/As per Design
Specification |
STEP |
ACTION |
1 |
Measure the clean room or clean zone
non-viable particulate counts at rest [before disturbing the area for
Recovery test]. |
2 |
Shut OFF the AHU of required zone. |
3 |
Allow the required zone to reach next higher
grade (i.e. Grade B To Grade C). |
4 |
Measure the non-viable particulate counts when
area achieve the next higher grade with help of particle counter for one day. |
5 |
Continue the particle counting for at least 5
counts. |
6 |
Start the AHU and measure the particle counts
till it the area achieves the desired level of counts approximately
equivalent to the initial counts taken at rest before the test. |
7 |
Measure time taken to recovery the initial
grade. |
8 |
Record the results and enclose the particle
count printouts and calculate the recovery time as-
|
9 |
Record the result [Reference is made to Annexure-V]. |
CRITERIA |
ACCEPTANCE |
Differential
pressure of rooms |
As
per design sheet + 0.5 mm of water |
PROCEDURE:
STEP |
ACTION |
1 |
All HVAC systems of the clean room facility
are to be in continuous operation when performing these tests. |
2 |
To avoid unexpected changes in pressure and to
establish baseline, all doors in sterile facility must be closed and no traffic
is to be allowed through the facility during the test. |
3 |
Adjust the Magnehelic gauge to give a reading
of zero in accordance with the manufacturer’s instructions. |
4 |
Connect one end of the tubes to the
higher-pressure side of the Magnehelic gauge(Calibrated) & place the
other end of the tube in the area of higher pressure such that it is free
from obstruction and directed away from any airflows. |
5 |
Next, connect one end of the second tube to
the lower pressure input side of the Magnehelic gauge and place the other end
of the tube in the area of lower pressure such that it is free from
obstruction and directed away from any airflows. If the tubing passes a
surface ensure that any gap surrounding the tube are sealed. |
6 |
Record the pressure displayed on the Magnehelic
gauge three times, for design differential pressure. |
7 |
Record the result [Reference is made to
Annexure-VII]. |
CRITERIA |
ACCEPTANCE |
Temperature
of controlled areas |
NMT
25℃ |
PROCEDURE
STEP |
ACTION |
1 |
Verify that the air conditioning system is
operating in the stable condition and all equipment that is specified is
running. |
2 |
Divide the room area in four equal zones test
as required by the specification or on a grid pattern of 3m x 3m. |
3 |
Use calibrated Data logger to record the
temperature. |
4 |
Record the temperature for location in each room. |
5 |
Record the result [Reference is made to
Annexure-VI]. |
CRITERIA |
ACCEPTANCE |
Relative
humidity in critical area |
NMT 50 % |
Relative
humidity in controlled area |
NMT 55% |
PROCEDURE:
STEP |
ACTION |
1 |
Execute humidity control test after all the
air balancing procedure have been concluded and air conditioning system is
completely in operation and stable conditions have been achieved |
2 |
Use calibrated Data Logger to record the
relative humidity. |
3 |
Record the relative humidity in room as per
layout of relative humidity record in each room. |
4 |
Record the result for three consecutive days
[Reference is made to Annexure-VI]. |
CRITERIA |
ACCEPTANCE |
Light
level |
Not
less than 300 lux / As per Design Specification |
STEP |
ACTION |
1 |
Record the light levels on a pre-determined
grid pattern/ layout of lux level or in the absence of a specification on a
3m x 3m grid pattern. |
2 |
Divide the room into four equal locations. |
3 |
Record the light level at working height or
750 mm above finished floor height. |
4 |
The area under test must have all fitted
lights working and the area structure should be complete also if required
emergency lighting levels can be recorded. |
5 |
Record the light levels in lux for each
position on the grid [Reference is made to Annexure VII]. |
6 |
Note down all variations from the
specification if any. |
CRITERIA |
ACCEPTANCE |
Noise
level |
Not
more than 85 dB / As per Design Specification |
PROCEDURE
STEP |
ACTION |
1 |
Verify that the air conditioning system is
operating in the stable condition and all equipment that is specified is
running [In operational condition]. |
2 |
Map out the area under test as required by the
specification in a 2400 mm x 2400 mm x grid or on a previously agreed
location basis i.e divide the area into fur equal parts. |
3 |
Set the instrumentation to work and ensure
unauthorized entry and exits from the room are prevented. |
4 |
Measure the sound levels at work surface
height or 750 mm from the finished floor level and layout of noise level. |
5 |
Record the data [Reference is made to
Annexure- VII]. |
6 |
Note down all variations from the
specification if any. |
- The protocol should be signed off (prior to start validation activities).
- Under responsibility of the Validation Head, Performance Qualification will be executed.
- After execution of required tests, the Validation Head should
- Check the results versus the Acceptance Criteria.
- Write the report.
- The report will be approved by the same persons (or same designations) who has Undersigned the protocol.
- The report should contain the following information:
- Report of all measurements and/or analytical results
- List of all documentation and or certifications.
- Check of the results against the Acceptance Criteria.
- Conclusions concerning this validation study
- Name and designations of persons who has executed the protocol
- Any (relevant) deviation from the prescriptions in this protocol and the Justification for the deviation.
20. REFERENCE
NO. |
CODE |
TITLE |
1 |
ISO 14644 |
Clean
Room & Associated Environment |
2 |
VMP-2006 |
Validation
Master Plan. |
3 |
SCH.M Pt.
I-A |
Drug
and Cosmetics act 1940. |
4 |
Annex 6 |
WHO
Technical report series No 902, 2002. |
5 |
USP |
2005
USP NF the Official compendia of standards. |
6 |
EC GUIDE |
EC
guide to good manufacturing practice annexure-1 September 2003. |
0 Comments